• September 26, 2008: All seeding and sodding for the Jack Nicklaus Signature Course is complete.

• Sept 9, 2008: Norm Provan, owner at Red Ledges, breaks ground on the first custom home.

• August 31, 2008: All Phase 1 and Phase 2 roads and utilities are completed.

• July 18, 2008: Cottage Homes Model Groundbreaking

• June 1, 2008: Began Sod/Seeding of Jack Nicklaus Signature Course

• May 15, 2008: Cart path installation started.

• May 13, 2008: All water and sewer services stubbed to Phase I homesites.

• May 13, 2008: All utilities and water lines in place for first phase

• April 15, 2008: Golf irrigation pump station installed.

• April 1, 2008: Canal work completed throughout Red Ledges

• March 20, 2008: All Sewer piping complete

• March 15, 2008: 85% of Water and Sewer lines in place

• November 15, 2007: 16 holes graded and shaped on the Jack Nicklaus Signature course

• September 16, 2007: 14 holes of the Jack Nicklaus Signature course graded

• September 1, 2007: Architectural design of Golf Clubhouse approved

• June 18, 2007: Jack Nicklaus Signature Golf Course construction begins

• May 10, 2007: Preliminary Plan approval given by Heber City

• March 15, 2007: Master Plan and Annexation approval given by Heber City

Planned:

• Late July/August 2008: All roads completed. Building permits can be pulled for custom homes